Rule Ot Thumb No 4 Feasibility Study

تقليص
X
 
  • تصفية - فلترة
  • الوقت
  • عرض
إلغاء تحديد الكل
مشاركات جديدة

  • Rule Ot Thumb No 4 Feasibility Study

    Cost The cost of a detailed feasibility study will be in a range from ½% to 1½% of the total estimated project cost. Source: Frohling and Lewis

    6.02 Cost The cost of a detailed or “bankable” feasibility study is typically in the range of 2% to 5% of the project, if the costs of additional (in-fill) drilling, assaying, metallurgical testing, geotechnical investigations, environmental scrutiny, etc. are added to the direct and indirect costs of the study itself. Source: R. S. Frew

    6.03 Time The definitive feasibility study for a small, simple mining project may be completed in as little as 6-8 weeks. For a medium-sized venture it may take 3-4 months, and a large mining project will take 6-9 months. A world-scale mining project may require more than one year. Source: Bob Rappolt and Mike Gray

    6.04 Accuracy ±15% accuracy of capital costs in a detailed feasibility study may be obtained with 15% of the formal engineering completed; ±10% accuracy with 50% completed and ±5% accuracy may be obtained only after formal engineering is complete. Source: Frohling, Lewis and others

    6.05 Production Rate The production rate (scale of operations) proposed in a feasibility study should be approximately equal to that given by applying Taylor’s Law. (Refer to Section 6.6)

    6.06 Production Rate Annual production should be one-third of the tons per vertical foot times 365 days in a year for a steeply dipping ore body. Source: Ron Cook

    6.07 Production Rate In the case of an orebody that is more or less vertical, the daily tonnage rate may approximate 15% of the tonnes indicated or developed per vertical meter of depth. Source: Northern Miner Press

    6.08 Production Rate At many mines, the annual production is equal to 30 vertical meters of ore. Others vary between 25 and 40 meters. Source: Wayne Romer

    6.09 Production Rate For a steeply dipping orebody, annual production should not exceed 30 to 40 meters of mine depth. Source: Robin Oram

    6.10 Production Rate For a steeply dipping ore body, the production rate
    should not exceed 60 meters (vertical) for a small mine. At mines producing over two million tons per year, 30-35 meters per year represents observed practice. Source: McCarthy and Tatman

    6.11 Development Preproduction development should be six months ahead of production. Source: METSInfo
    6.12 Development Six months of production ore should be accessible at all times to ensure stope scheduling and blending. Source: Kirk Rodgers

المواضيع ذات الصلة

تقليص

المواضيع إحصائيات آخر مشاركة
أنشئ بواسطة HaMooooDi, 09-14-2024, 03:55 PM
ردود 0
34 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
أنشئ بواسطة HaMooooDi, 09-14-2024, 03:49 PM
ردود 0
15 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
أنشئ بواسطة noor maha, 07-22-2024, 02:02 PM
ردود 0
41 مشاهدات
0 معجبون
آخر مشاركة noor maha
بواسطة noor maha
 
أنشئ بواسطة noor maha, 07-22-2024, 02:00 PM
ردود 0
11 مشاهدات
0 معجبون
آخر مشاركة noor maha
بواسطة noor maha
 
أنشئ بواسطة HaMooooDi, 06-04-2024, 08:23 PM
ردود 0
45 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
يعمل...
X